Is it compulsory for the Promoter to register the Project immediately after he gets sanction / commencement certificate?

No. Promoter has to register the Project before he starts any form of advertising or selling the units and not after getting the building plan sanctioned / commencement certificate.
Hence a promoter can start his construction, complete his show flat, excavation and any other construction he desires and then register the project under RERA.